Microsoft Project Issue with Clarity V13
we
recently upgraded from V12.1 to V13 and everything works fine except the
Microsoft Project Schedule.
When we try to export to MSP it opens up in MSP and downloads all the task and related information which we could see. Immediate after that it says removing says and all the task populated is getting removed and stays blank.
Not sure anyone face this issue.
Appreciate your feedback on this.
When we try to export to MSP it opens up in MSP and downloads all the task and related information which we could see. Immediate after that it says removing says and all the task populated is getting removed and stays blank.
Not sure anyone face this issue.
Appreciate your feedback on this.
Answer
We had a user with some issues
using MSP 2007 and Clarity...we upgraded to MSP 2010 and problem solved. What
we did: Upgrade to MSP 2010, then re-install the connector (MSP/Clarity)