Microsoft Project Issue with Clarity V13
we recently upgraded from V12.1 to V13 and everything works fine except the Microsoft Project Schedule.

When we try to export to MSP it opens up in MSP and downloads all the task and related information which we could see. Immediate after that it says removing says and all the task populated is getting removed and stays blank.
Not sure anyone face this issue.

Appreciate your feedback on this. 

Answer

We had a user with some issues using MSP 2007 and Clarity...we upgraded to MSP 2010 and problem solved. What we did: Upgrade to MSP 2010, then re-install the connector (MSP/Clarity)