Which conditions need to be met to convert an existing project to a program? (Choose two)
A.The project contains no staff.
B. The project contains no tasks.
C. The project contains no schedule.
D. The project contains no milestones.
Answer is A and B
The reason behind this and in Clarity , We can't assign resources and tasks at the program level and only we can create milestone.