Resource X availability is 8 hrs per day.
2)
Resource X, 50% allocated for X Project,
75% allocated for Y
100%
Allocated for Z Project.
X
project : 4 hrs day , Resource X Availability : 8 hrs per day (also
it will consider calendar and date of hire)
Y
Project : 6 hrs day
Z project
: 8 hrs day
Note :
it could be for different period.
% Allocation =
(allocated
Hrs per Day for particular project)/Availability Hrs per day
(4/8)*100
= 50%
(6/8)*100
= 75%
(8/8)*100
= 100%
Regards,
Bala