Resource Allocation Calculation


) Resource X availability is 8 hrs per day.        

2) Resource X,  50% allocated for X Project,

    75% allocated for Y 

100% Allocated for Z Project.  

 
Allocated Hrs Per Day:                           

X project : 4 hrs day , Resource X Availability : 8 hrs per day   (also it will consider calendar and date of hire)

Y Project : 6 hrs day

Z project : 8 hrs day


Note : it could be for different period.


 % Allocation =

(allocated Hrs per Day for particular project)/Availability Hrs per day

 

(4/8)*100 = 50% 

 

(6/8)*100 = 75% 

 

(8/8)*100 = 100% 